Our Terms are Fair and Transparent...

General Terms for Electrical Work

MATTHEW BRAY ELECTRICAL - STANDARD TERMS AND CONDITIONS FOR ELECTRICAL WORK;

1. INSTALLATION WORK

a) All electrical installation work shall comply with BS7671 and any amendment in force at the time of the works

b) All electrical installation work will comply with applicable building regulations in force at the time of the works

c) Where work is to extend or modify existing circuits, any costs quoted assume that the existing installation in in adequate

condition and complies with minimum current regulations. Any additional works required to bring the installation up to standard 

will be at additional cost

d) Unless otherwise stated, all cables will be concealed by chasing into the building fabric or concealed in building voids, under

floor etc. Where impractical, cabling will be neatly surface run, either in trunking or clipped direct

e) Where carpet or floor covering may require lifting and relaying to allow concealed installation work, no charge is made for 

this service, with best endeavours being made to avoid damaging them and to refit them to an acceptable standard. However, 

consideration of employing a specialist fitter may be prudent, at your cost, to effect a fully satisfactory reinstatement.

f) Where agreed beforehand, chases to walls etc will be re-filled to 1mm above plaster finish height using 'Easy-fill' and it is left 

to the client to sand down flat on completion. Decoration is excluded.

g) All endeavours will be made to undertake installation work to a clean standard, however we wish to make the customer 

aware that they will need to vacuum and wipe surface with a damp cloth to remove dust on completion

h) The duration of these works should be discussed during booking

i) Whilst undertaking works at the property, the client is required to provide water and power free of charge

2. EXCLUSIONS

a) Clearing and/or moving of furniture and other items blocking access to areas of work are not included - Please have the 

rooms empty and clear of clutter ready for our arrival

b) Except where specifically detailed, builders work (creating holes of larger that 25mm diameter, creating of support structures 

etc) are not included, except as outlined in 1d,e and f above

c) Redecoration and final making good is excluded from quoted costs unless specifically detailed as included

d) Removal from site and disposal of rubble, fittings, wiring, materials, general waste and packaging is not included

3. EXTRAS AND VARIATIONS

a) All extras and variations must be agreed in writing prior to commencement.

4. PRICING

a) The costs quoted assume continuous and unhindered access to the site by prior arrangement with you.

b) Unless specifically detailed otherwise in the quotation, the costs assume standard working hours of 08.00am-18.00pm 

Monday to Friday inclusive. Work required outside of these hours may attract out of hours premium rates.

c) Any additional works not covered in our quoted costs attract additional time charge of £50.00 per hour plus material costs

and VAT

d) All rates quoted are subject to VAT at the prevailing rate

e) All figures quoted are valid for 30 days from the date of the quotation

5. DEVIATIONS FROM BUILDING REGULATIONS & BS7671

a) All work, where applicable, will be executed fully in compliance with the applicable building regulations and BS7671 in force 

at the time of work, particularly in respect of work in dwellings to allow the legal part P obligations to be met. Where a client 

requires deviation from such regulations, a written instruction and record will be required.

6. RISK AND TITLE OF GOODS AND PROPERTY

a) The risk in all goods supplied shall pass to the client upon delivery

b) All goods supplied shall remain the property of The Bray Collective Ltd t/a Matthew Bray Electrical until all sums due have 

been paid in full

c) The client is responsible for ensuring the property is insured for the duration of the works

7. WARRANTY

a) The Bray Collective Ltd warrants it's installation work to be defect free for a period of 12 months from invoice date. Any such 

cover does not extend to goods not supplied by us, physical damage (whether deliberate or accidental) to products, or any 

instance where the original installation has been altered or tampered with subsequently by third parties.

8. PAYMENT

a) Unless agreed in writing, full payment must be made on completion of the specified works to The Bray Collective Ltd

b) Stage payments may be requested where planned works take longer than 7 days.

c) Deposits taken are non-refundable. If the client cancels or postpones works within 48 hours of the planned start date and 

time, a further deposit may be required on re-booking. Deposits taken for special order items are non-refundable

9. DISPUTE RESOLUTION

a) In the event of a dispute, mediation is to be the preferred method of resolution


IF YOU NEED TO SPEAK TO US ON THE TELEPHONE, PLEASE CALL US ON (07887) 535484